Carseldine Village
FOR THE LATEST INFORMATION go to carseldinevillage.com.au
Carseldine Village, a new residential community on Brisbane’s northside, is being developed by Economic Development Queensland (EDQ), a government agency that combines property development with specialist planning functions, on the site of the former QUT campus at Carseldine.
Carseldine Village will be an exemplar of sustainable development – the first residential development in Queensland to commit to delivering 100% net-zero energy emission homes with energy-saving features.
On completion, the new village will consist of mixed-use, diverse, and affordable residential, small commercial and retail, along with bushland and recreational open space areas.
At CarseldineContinue reading
FOR THE LATEST INFORMATION go to carseldinevillage.com.au
Carseldine Village, a new residential community on Brisbane’s northside, is being developed by Economic Development Queensland (EDQ), a government agency that combines property development with specialist planning functions, on the site of the former QUT campus at Carseldine.
Carseldine Village will be an exemplar of sustainable development – the first residential development in Queensland to commit to delivering 100% net-zero energy emission homes with energy-saving features.
On completion, the new village will consist of mixed-use, diverse, and affordable residential, small commercial and retail, along with bushland and recreational open space areas.
At Carseldine Village, 75 per cent of the bushland is being retained and there are more than 18 hectares of green and open space. The Cabbage Tree Creek bushland, called The Sanctuary, is going through rehabilitation works with the planting of 20,000 new plants, trees and shrubs, and the installation of over 200 nesting boxes.
The masterplan for Carseldine Village is proposed to be developed in 5 stages. The current approved masterplan provides for a maximum of 606 dwellings. In one of the future stages, a village retail heart will potentially comprise a convenience supermarket, specialty retail and dining.
The Government Office Precinct, C&K Child Care Centre, and Carseldine Markets remain.
Construction update
Stage 1 construction includes:
- Stage 1 terrace homes - complete.
- Stage 1 civil and electrical works - complete.
- A new entry road into Carseldine Village, called Plaza Place - complete
- The three intersection upgrades to Beams and Dorville Roads - complete
- Rockpool Residential Aged Care - complete.
Stage 2 construction includes:
- Stage 2 terrace homes - under construction.
- Stage 2 civil and electrical works - complete.
Stage 3A construction includes:
- Stage 3A terrace homes - under construction.
- Stage 3A civil and electrical works - complete.
Stage 4A construction includes:
- Stage 4A civil and electrical works - complete.
Stage 4B construction includes:
- Stage 4B and 4C civil and electrical works - complete.
Stage V construction includes:
- Stage V scope of works includes service relocations, demolition of existing C&K building, vegetation clearning, earthworks, underground service installation, retaining wall construction, roadworks, and landscape works. Works are underway
Stage releases
Stage 1 which includes 53 terrace homes is sold out.
Stage 2 which includes 49 terrace homes is sold out.
Stage 3A which includes 15 terrace homes is sold out.
4A Release which includes 10 terrace homes is sold out.
4B Release which includes 13 terrace homes is sold out.
4C Release is now selling with one terrace house and land package remaining.
For enquiries or information, please email hello@carseldinevillage.com.au
The Green
The Green, a new $6.5 million sport and recreation precinct that stretches over four hectares and incorporates the latest technology opened on 11 January 2020.
The Green includes three soccer fields (of which two are dual-purpose soccer/rugby league); two volleyball courts; two dual-purpose tennis/netball courts; a half-court basketball court; an outdoor ping pong table; a turf cricket pitch and synthetic practice nets; an all-abilities playground; yoga lawn; exercise equipment; BBQs, shaded seating, public toilets, and sports change room facilities and more than 120 car parks.
Bookings for the sports facilities at The Green can be made via the Carseldine Village website.
Rockpool Residential Aged Care
Rockpool Residential Aged Care is now open.
A $43 million Residential Aged Care facility. This 6-level, 150-bed accommodation and care facility will offer aged care, respite care and specialist memory support care.
The Rock's Cafe, located on the ground floor of Rockpool Residential Aged Care is also open.
C&K Childcare
The brand-new C&K Childcare Centre next to Rockpool Residential Aged Care is now open.
This new intergenerational care collaboration is a pioneering step towards better social outcomes and innovating the social fabric within residential villages across Queensland.
This new Centre will create opportunities for meaningful social interactions, integrating new ideas to add to the quality of life and social development benefits for the community.
More information
For more information on Carseldine Village, please visit our website on:
View the Carseldine Village development applications below:
EDQ reference | Description |
Stage S – The Green sport and recreation precinct | |
Masterplan for Carseldine Village | |
Management lot subdivision | |
Cabbage Tree Creek pedestrian and cycle bridge | |
Stage 1 – Terrace lots and aged care/retirement lot | |
Stage 2 – Terrace lots |
Q and A
Please review the responses below, as your question may already be answered. If you would like to ask us a new question about the Carseldine Village project, please do so here.
-
Share Could you PLEASE correct the street signs so they reflect the plans? on Facebook Share Could you PLEASE correct the street signs so they reflect the plans? on Twitter Share Could you PLEASE correct the street signs so they reflect the plans? on Linkedin Email Could you PLEASE correct the street signs so they reflect the plans? link
Could you PLEASE correct the street signs so they reflect the plans?
RG asked almost 2 years agoThank you for making us aware of this, the signage has now been updated. Any further concerns please email hello@carseldinevillage.com.au
-
Share Could you please advise when stage 4 A will start building? on Facebook Share Could you please advise when stage 4 A will start building? on Twitter Share Could you please advise when stage 4 A will start building? on Linkedin Email Could you please advise when stage 4 A will start building? link
Could you please advise when stage 4 A will start building?
Rus asked almost 2 years agoHello, construction of the homes in Stage 4A has commenced. For more information on the build programs please reach out to your builder.
#building #houseandland#building #houseandland -
Share I am very much interested in this development and want to book one for us, I have already done bank finance pre-approval, please let me know what is the process involve and what I have to do next. on Facebook Share I am very much interested in this development and want to book one for us, I have already done bank finance pre-approval, please let me know what is the process involve and what I have to do next. on Twitter Share I am very much interested in this development and want to book one for us, I have already done bank finance pre-approval, please let me know what is the process involve and what I have to do next. on Linkedin Email I am very much interested in this development and want to book one for us, I have already done bank finance pre-approval, please let me know what is the process involve and what I have to do next. link
I am very much interested in this development and want to book one for us, I have already done bank finance pre-approval, please let me know what is the process involve and what I have to do next.
Kamal asked over 3 years agoHi Kamal, you can contact our sales team to discuss further via phone, email, or in person. Details below:
Address: Carseldine Village Sales and Information Centre, 520 Beams Road, Carseldine (open Fridays - Tuesdays 10am-4pm).
Phone: 1300 647 123
Email: hello@carseldinevillage.com.au
-
Share Is there a skate facility being built within The Green? If not, could I please ask why? Thanks, Anthony. on Facebook Share Is there a skate facility being built within The Green? If not, could I please ask why? Thanks, Anthony. on Twitter Share Is there a skate facility being built within The Green? If not, could I please ask why? Thanks, Anthony. on Linkedin Email Is there a skate facility being built within The Green? If not, could I please ask why? Thanks, Anthony. link
Is there a skate facility being built within The Green? If not, could I please ask why? Thanks, Anthony.
ABurgess asked over 4 years agoHi Anthony, following public consultation with local residents and sporting groups in 2017, EDQ designed the new sport and recreation precinct (The Green) based on community feedback. In addition to an onsite engagement session, an online survey, local newspaper advertisement, newsletter to 8,400 homes, and letters to 23 sporting groups were carried out. A skate park wasn’t a facility that was highly sought-after. There is however Bracken Ridge Skate Plaza which is located 11 minutes down the road.
#sportandrecreation ,#skate,#thegreen#sportandrecreation #skate #thegreen -
Share The bridge over cabbage tree creek and the pathway on the Carseldine side was completed a few weeks ago but the path is still blocked off. Access to the bridge on the Aspley High School side appears to be blocked because of the construction works on the new buildings at the school, which I understand might not be completed until April 2021. Is pedestrian access going to be blocked until then? on Facebook Share The bridge over cabbage tree creek and the pathway on the Carseldine side was completed a few weeks ago but the path is still blocked off. Access to the bridge on the Aspley High School side appears to be blocked because of the construction works on the new buildings at the school, which I understand might not be completed until April 2021. Is pedestrian access going to be blocked until then? on Twitter Share The bridge over cabbage tree creek and the pathway on the Carseldine side was completed a few weeks ago but the path is still blocked off. Access to the bridge on the Aspley High School side appears to be blocked because of the construction works on the new buildings at the school, which I understand might not be completed until April 2021. Is pedestrian access going to be blocked until then? on Linkedin Email The bridge over cabbage tree creek and the pathway on the Carseldine side was completed a few weeks ago but the path is still blocked off. Access to the bridge on the Aspley High School side appears to be blocked because of the construction works on the new buildings at the school, which I understand might not be completed until April 2021. Is pedestrian access going to be blocked until then? link
The bridge over cabbage tree creek and the pathway on the Carseldine side was completed a few weeks ago but the path is still blocked off. Access to the bridge on the Aspley High School side appears to be blocked because of the construction works on the new buildings at the school, which I understand might not be completed until April 2021. Is pedestrian access going to be blocked until then?
Bill asked over 4 years agoThe $1million pedestrian/cycle bridge within Carseldine Village is now complete and is due to open for use to the public soon.
The Department of Education have advised there is a path from Aspley State High School south-west of the bridge, that goes around the pool so students will be able to use the new bridge and path to access the school. During the balance of the Stage 1 civil works at Carseldine Village which are expected to be completed by the end of 2020, this will be via the pre-existing pathway accessed from the Dorville Road entry north-west of the bridge.
#bridge#bridge -
Share I'm concerned on the impact of our schools especially Aspley High School which is already at a high Capacity. Dorville road is usually congested all the way from the roundabout up to Zillmere road during the school runs as it is. If our local schools are already at full capacity where are these new students expected to go? How are you going to combat the extra traffic on Dorville road? on Facebook Share I'm concerned on the impact of our schools especially Aspley High School which is already at a high Capacity. Dorville road is usually congested all the way from the roundabout up to Zillmere road during the school runs as it is. If our local schools are already at full capacity where are these new students expected to go? How are you going to combat the extra traffic on Dorville road? on Twitter Share I'm concerned on the impact of our schools especially Aspley High School which is already at a high Capacity. Dorville road is usually congested all the way from the roundabout up to Zillmere road during the school runs as it is. If our local schools are already at full capacity where are these new students expected to go? How are you going to combat the extra traffic on Dorville road? on Linkedin Email I'm concerned on the impact of our schools especially Aspley High School which is already at a high Capacity. Dorville road is usually congested all the way from the roundabout up to Zillmere road during the school runs as it is. If our local schools are already at full capacity where are these new students expected to go? How are you going to combat the extra traffic on Dorville road? link
I'm concerned on the impact of our schools especially Aspley High School which is already at a high Capacity. Dorville road is usually congested all the way from the roundabout up to Zillmere road during the school runs as it is. If our local schools are already at full capacity where are these new students expected to go? How are you going to combat the extra traffic on Dorville road?
JUS-1337 asked almost 5 years agoAs part of any significant development project, a traffic impact assessment is necessary. The documentation submitted for the Carseldine Village Stage 1 PDA development application included the required analysis. The proposed traffic management measures were rigorously assessed and approved. These measures include upgrades to three external intersections, one of which is on Dorville Road, with their construction commencing shortly. The Stage 1 traffic advice can be found online searching (DEV2019/1074).
Please also note on 20 June 2020, the Queensland Government committed a further $128 million towards addressing safety and congestion at Beams Road. Construction of the $233 million level crossing overpass could commence as early as December 2021, subject to funding contributions from Brisbane City Council and the Australian Government. See here
In relation to your query around school capacity, the Queensland Department of Education https://education.qld.gov.au/contact-us would be best placed to discuss these matters.
#traffic#traffic -
Share I note with interest the construction of a bridge to Aspley High School - I think this is a great idea. Will the undergrowth around the track and bridge be cleared to allow clear sight from the carpark and Carseldine Green to improve personal security for young high school girls in particular using the track? on Facebook Share I note with interest the construction of a bridge to Aspley High School - I think this is a great idea. Will the undergrowth around the track and bridge be cleared to allow clear sight from the carpark and Carseldine Green to improve personal security for young high school girls in particular using the track? on Twitter Share I note with interest the construction of a bridge to Aspley High School - I think this is a great idea. Will the undergrowth around the track and bridge be cleared to allow clear sight from the carpark and Carseldine Green to improve personal security for young high school girls in particular using the track? on Linkedin Email I note with interest the construction of a bridge to Aspley High School - I think this is a great idea. Will the undergrowth around the track and bridge be cleared to allow clear sight from the carpark and Carseldine Green to improve personal security for young high school girls in particular using the track? link
I note with interest the construction of a bridge to Aspley High School - I think this is a great idea. Will the undergrowth around the track and bridge be cleared to allow clear sight from the carpark and Carseldine Green to improve personal security for young high school girls in particular using the track?
Norm asked almost 5 years agoThe new bridge will provide a safe, active travel path for school children to cycle and walk to school, including lighting on the bridge and along a new section of path which connects with the existing pathway on the north side of Cabbage Tree Creek.
In regards to vegetation removal EDQ have followed Brisbane City Council standards in relation to the proximity of vegetation to pedestrian/cycle paths for public safety, as well as vegetation protection.
#bridge,#pedestriancyclebridge#bridge #pedestriancyclebridge -
Share re Stormwater Thank you for answering my question. 1) What plans are in place to increase the capacity of the Cabbage Tree Creek on the Fitzgibbon side. Some minimal work was done after I complained after the floods in 2012 when the whole place was submerged and the reserve land was almost 4 feet under. But I do not think it is enough. The amount of soil dumped there now looks like a small mountain. 2) Also I reckon before any work is to start there, the traffic should be taken care of. I do not mean putting in 'slow-down' signs but real care, like increasing the lanes. Someone is only interested in making money(houses) but not spending for public (roads, level crossing). 3) All funds are being spent in the city and south. Even the recent work on Beams Rd - near the golf range looks like a waste of money and time. Thanks Please let me know on Facebook Share re Stormwater Thank you for answering my question. 1) What plans are in place to increase the capacity of the Cabbage Tree Creek on the Fitzgibbon side. Some minimal work was done after I complained after the floods in 2012 when the whole place was submerged and the reserve land was almost 4 feet under. But I do not think it is enough. The amount of soil dumped there now looks like a small mountain. 2) Also I reckon before any work is to start there, the traffic should be taken care of. I do not mean putting in 'slow-down' signs but real care, like increasing the lanes. Someone is only interested in making money(houses) but not spending for public (roads, level crossing). 3) All funds are being spent in the city and south. Even the recent work on Beams Rd - near the golf range looks like a waste of money and time. Thanks Please let me know on Twitter Share re Stormwater Thank you for answering my question. 1) What plans are in place to increase the capacity of the Cabbage Tree Creek on the Fitzgibbon side. Some minimal work was done after I complained after the floods in 2012 when the whole place was submerged and the reserve land was almost 4 feet under. But I do not think it is enough. The amount of soil dumped there now looks like a small mountain. 2) Also I reckon before any work is to start there, the traffic should be taken care of. I do not mean putting in 'slow-down' signs but real care, like increasing the lanes. Someone is only interested in making money(houses) but not spending for public (roads, level crossing). 3) All funds are being spent in the city and south. Even the recent work on Beams Rd - near the golf range looks like a waste of money and time. Thanks Please let me know on Linkedin Email re Stormwater Thank you for answering my question. 1) What plans are in place to increase the capacity of the Cabbage Tree Creek on the Fitzgibbon side. Some minimal work was done after I complained after the floods in 2012 when the whole place was submerged and the reserve land was almost 4 feet under. But I do not think it is enough. The amount of soil dumped there now looks like a small mountain. 2) Also I reckon before any work is to start there, the traffic should be taken care of. I do not mean putting in 'slow-down' signs but real care, like increasing the lanes. Someone is only interested in making money(houses) but not spending for public (roads, level crossing). 3) All funds are being spent in the city and south. Even the recent work on Beams Rd - near the golf range looks like a waste of money and time. Thanks Please let me know link
re Stormwater Thank you for answering my question. 1) What plans are in place to increase the capacity of the Cabbage Tree Creek on the Fitzgibbon side. Some minimal work was done after I complained after the floods in 2012 when the whole place was submerged and the reserve land was almost 4 feet under. But I do not think it is enough. The amount of soil dumped there now looks like a small mountain. 2) Also I reckon before any work is to start there, the traffic should be taken care of. I do not mean putting in 'slow-down' signs but real care, like increasing the lanes. Someone is only interested in making money(houses) but not spending for public (roads, level crossing). 3) All funds are being spent in the city and south. Even the recent work on Beams Rd - near the golf range looks like a waste of money and time. Thanks Please let me know
kartom asked almost 5 years ago1) This development does not include works in Cabbage Tree Creek for stormwater management.
All stormwater management measures are delivered internal to the development, and include, amongst other measures, a new 1,200mm diameter stormwater pipe in the main entry boulevard. This pipe and the other proposed measures appropriately manage the stormwater impacts from the development without any works being required in Cabbage Tree Creek.2) As part of any significant development project, a traffic impact assessment is necessary. The documentation submitted for the Carseldine
Village Stage 1 PDA development application included the required analyses. The proposed traffic management measures were rigorously assessed
and approved. These measures include upgrades to three external intersections, with their construction commencing shortly. The Stage 1 traffic
advice can be found online searching (DEV2019/1074).
Works on the three external intersections included in Stage 1, which are (in part) outside the Fitzgibbon Priority Development Area, are also subject
to Council approvals which have now been granted.
Please also note the Department of Transport and Main Roads is currently undertaking a planning study on the Beams Road level rail crossing to
investigate options to reduce congestion and address safety concerns. Information is provided on their Beams Road (Carseldine) rail level
crossing project website here.
#stormwater,#traffic,#railcrossing#stormwater #traffic #railcrossing -
Share Hi team Could you please provide an update on the development application for subdivision of Stage 1. Is this still progressing? on Facebook Share Hi team Could you please provide an update on the development application for subdivision of Stage 1. Is this still progressing? on Twitter Share Hi team Could you please provide an update on the development application for subdivision of Stage 1. Is this still progressing? on Linkedin Email Hi team Could you please provide an update on the development application for subdivision of Stage 1. Is this still progressing? link
Hi team Could you please provide an update on the development application for subdivision of Stage 1. Is this still progressing?
Vi asked over 5 years agoDevelopment applications to amend the Carseldine Urban Village Masterplan, and for the Stage 1 development, were lodged in October 2019. The applications can be viewed here https://bit.ly/33W98eO by searching DEV2018/932/3 (Masterplan amendment) and DEV2019/1074 (Stage 1 development). A public notification period for both applications is to run for a 22 business day period from 20 November to 19 December 2019, giving the community a formal process to have their say on the proposals.
#developmentapplication,#stage1#developmentapplication #stage1 -
Share Why is there an open day being advertised and a display unit built on site already? This development is still not approved and is still open to public feedback. Is this feedback going to be listened to at all? Or will the development of the site go ahead regardless of local opposition? on Facebook Share Why is there an open day being advertised and a display unit built on site already? This development is still not approved and is still open to public feedback. Is this feedback going to be listened to at all? Or will the development of the site go ahead regardless of local opposition? on Twitter Share Why is there an open day being advertised and a display unit built on site already? This development is still not approved and is still open to public feedback. Is this feedback going to be listened to at all? Or will the development of the site go ahead regardless of local opposition? on Linkedin Email Why is there an open day being advertised and a display unit built on site already? This development is still not approved and is still open to public feedback. Is this feedback going to be listened to at all? Or will the development of the site go ahead regardless of local opposition? link
Why is there an open day being advertised and a display unit built on site already? This development is still not approved and is still open to public feedback. Is this feedback going to be listened to at all? Or will the development of the site go ahead regardless of local opposition?
Vanessa asked over 5 years agoThe Community Open Day on 1 Feb is to celebrate the approved and completed $6.5m brand new sport and recreation precinct (Stage S).
In regards to future development of the site the development applications (DA) for an amendment to the Carseldine Urban Village Masterplan, and Stage 1 development, were lodged in October 2019.A range of reports and documents were prepared for, and submitted with, the development applications including but not limited to a town planning report, proposal plans, landscape plans, civil engineering report, stormwater management plan, traffic impact assessment and ecological assessment.
The applications can be viewed online by searching DEV2018/932/3 (Masterplan amendment) and DEV2019/1074 (Stage 1 residential subdivision).
The Masterplan amendment application looks to formalise the location of the village heart for the Carseldine Urban Village on the western side of the entry boulevard. The Village Heart will provide for a local active retail, commercial and mixed use precinct that links the existing Government Office Precinct, with the new residential development and the new sporting facilities, all a shortwalk to the Carseldine Train Station.
The Stage 1 residential subdivision proposes 53 terrace housing lots and one mixed use allotment. The development will also propose one retirement / aged care development allotment which will be subject to a separate future development application. The terrace homes:
- will deliver a contemporary built form, with individuality and diversity in design
- provide affordability for future residents, with all homes required to achieve a minimum 7-star energy rating
- achieve a minimum Silver level of the Liveable Housing Design Guidelines, making them safer and easier to use for all people including: those with disability and ageing Australians
- provide privacy for the residents, while presenting attractively to the street.
A public notification period for both applications is to run for a 22 business day period from 20 November to 19 December 2019, giving the community a formal process to have their say on the proposals.
The Carseldine Village Sales and Information Centre is under construction. Works onsite will occur over the next two months. The building is temporary and not fixed, therefore if an approval isn’t awarded the building can be removed.
#traffic,#developmentapplication#traffic #developmentapplication
Project Timeline
-
July 2008
Carseldine Village has finished this stageFitzgibbon Priority Development Area (PDA) declared, identifying the Carseldine Urban Village site for renewal. Community consultation begins as the Development Scheme is prepared.
-
July 2009
Carseldine Village has finished this stageFitzgibbon PDA development scheme adopted. It is identified that further planning work around the Carseldine Urban Village needed to be undertaken
-
2010 - 2011
Carseldine Village has finished this stageFurther, extensive community engagement undertaken around Carseldine Urban Village site, including the establishment of the Carseldine Community Liaison Group, community newsletters, community information sessions, and a public notification period.
-
July 2011
Carseldine Village has finished this stageAmendments (based on community engagement) to the Fitzgibbon PDA Development Scheme adopted.
-
October 2016
Carseldine Village has finished this stageThe Queensland Government launched the Advancing our cities and regions strategy, which will see surplus and underutilised state property renewed and repurposed. Under this strategy the Carseldine Urban Village is identified as the first SEQ urban renewal precinct to be revitalised.
-
December 2016
Carseldine Village has finished this stageEconomic Development Queensland invited the community to register for community consultation opportunities around the urban village's public realm (to be undertaken in February 2017).
December newsletter with project information was sent to Carseldine, Aspley and Fitzgibbon residents.
Community members could come and talk to Economic Development Queensland at Carseldine Markets on Saturday 3, 10 or 17 December and register for February's community consultation.
Two quick polls were run to tell us what day and time were most suitable for future community consultation.
-
January 2017
Carseldine Village has finished this stageJanuary newsletter with project information was sent to Carseldine, Aspley and Fitzgibbon residents and also is available to download online.
-
February 2017
Carseldine Village has finished this stageEconomic Development Queensland undertook four community engagement workshops in February on place making and community development opportunities within the Carseldine Urban Village. This will build on the existing land use plan to identify a vision for a viable, socially inclusive and sustainable development, now and in the future.
-
April 2017
Carseldine Village has finished this stageApril newsletter on proposed Sport and Recreation precinct is available for download.
-
May 2017
Carseldine Village has finished this stageCommunity engagement session on proposed Sport and Recreation precinct - Sunday 21 May.
Community newsletter No #4 summarising engagement outcomes to-date.
-
June 2017
Carseldine Village has finished this stageRegister for the master plan information sessions
- Sunday 18 June 9 am - 12 pm
- Sunday 18 June 1 - 4 pm
- Thursday 22 June 6.30 - 8.30 pm
-
July - August 2017
Carseldine Village has finished this stageStage S (sport and recreation) development application (DA) lodgement.
-
29 Oct - December 2017
Carseldine Village has finished this stageQueensland Government caretaker period, election and post election departmental changes.
-
May 2018
Carseldine Village has finished this stageApproval of stage S (sport and recreation).
Stage 1 development application (DA) lodgement.
-
mid-2018
Carseldine Village has finished this stageInformation sessions:
- Thursday 21 June 2018
- Saturday 23 June 2018
30 business day public notification period -
August 2018
Carseldine Village has finished this stagePublic notification of the master plan and Stage 1 development application – commences 9 August, concludes 20 September.
-
September 2018
Carseldine Village has finished this stagePublic notification concludes.
Stage S construction commencing. -
October 2018
Carseldine Village has finished this stageStage S construction commences and due for completion mid 2019. -
End 2018
Carseldine Village has finished this stageMaster plan development application approved.
-
October 2019
Carseldine Village has finished this stageAmendment to the overall masterplan and Stage 1 development applications lodged.
-
November / December 2019
Carseldine Village has finished this stageAmendment to the overall masterplan and Stage 1 development applications are publicly notified for a 22 business day period from 20 November to 19 December 2019, giving the community a formal process to have their say on the applications.
-
End 2019
Carseldine Village has finished this stageStage S complete.
-
January 2020
Carseldine Village has finished this stagePedestrian / cycle bridge construction works commenced.
-
February 2020
Carseldine Village has finished this stageThe brand new $6.5m sport and recreation precinct community day on 1 February – everyone is welcome. Further event details are available on carseldinevillage.com.au
-
February 2020
Carseldine Village has finished this stageSales and Information Centre opens. Visit carseldinevillage.com.au for opening hours.
-
April 2020
Carseldine Village has finished this stageStage 1 civil works commenced 27 April.
-
September 2020
Carseldine Village has finished this stageDevelopment Approval received for Stage 2.
-
October 2020
Carseldine Village has finished this stageCabbage Tree Creek pedestrian and cycle bridge opens.
-
Late 2020
Carseldine Village has finished this stageSuccessful developer for the aged care site announced – Rockpool Residential Aged Care.
-
Late 2020
Carseldine Village has finished this stageStage 2 civil and electrical work commenced.
-
May 2021
Carseldine Village has finished this stageStage 1 construction works complete.
-
May 2021
Carseldine Village has finished this stageNew entry road into Carseldine Village – called Plaza Place opened.
-
May 2021
Carseldine Village has finished this stageRockpool Residential Aged Care commenced construction.
-
August 2021
Carseldine Village has finished this stageCabbage Tree Creek bushland vegetation works are anticipated to be completed.
-
September 2021
Carseldine Village has finished this stageStage 2 civil and electrical works completed.
-
October 2021
Carseldine Village has finished this stageVillage Heart ROI was released.
-
October 2021
Carseldine Village has finished this stageStage 3 civil and electrical works commenced.
-
Early 2022
Carseldine Village has finished this stageStage 1 home owners start moving into their new terrace homes.
-
July 2022
Carseldine Village has finished this stageRockpool Residential Aged Care opens
-
July 2022
Carseldine Village has finished this stage4A House & Land Packages released
-
July 2022
Carseldine Village has finished this stageStage 2 Homes commence construction
-
August 2022
Carseldine Village has finished this stageStage 3A & 4A civil & electrical works completed
-
August 2022
Carseldine Village has finished this stageNew C&K Childcare Centre commences construction, completion due mid-2023
-
August 2022
Carseldine Village has finished this stage4B House & land packages released
-
March 2023
Carseldine Village has finished this stageStage 3 homes commence construction
-
March 2023
Carseldine Village has finished this stageStage 4B civil, electrical and landscaping works commence
-
July 2023
Carseldine Village has finished this stageBrand new C&K Childcare opens at Carseldine Village
-
August 2023
Carseldine Village has finished this stageStage V civil, electrical and landscaping works commence.
-
September 2023
Carseldine Village has finished this stageStage 4B civil and electrical works complete.
-
mid 2024
Carseldine Village is currently at this stageStage V works likely to be completed, subject to weather and/or industry delays
Notices
-
Carseldine Village - BMD Community Notice 1-19 September 2022.pdf (251 KB) (pdf)
-
Carseldine Village - Temporary Road Closure - Plaza Pl Carseldine (1.18 MB) (pdf)
-
Community Notice - Survey and Investigation Works - Beams Road.pdf (78.3 KB) (pdf)
-
Community Notice - Stage 4B and Catch Drain Works - Carseldine Village.pdf (520 KB) (pdf)
-
Community Notice - Stage V works - Carseldine Village.pdf (303 KB) (pdf)
Historical document library
-
CUV Newsletters and Fact sheets
-
Carseldine Urban Village newsletter May 2018 (1.62 MB) (PDF)
-
Carseldine Urban Village fact sheet Feb 2018 (1.01 MB) (pdf)
-
Carseldine Urban Village Newsletter Aug 2017 (1.83 MB) (pdf)
-
Carseldine Urban Village Newsletter May 2017 (1.27 MB) (pdf)
-
Carseldine Urban Village newsletter April 2017 (909 KB) (pdf)
-
Carseldine Urban Village newsletter Jan 2017 (742 KB) (pdf)
-
Carseldine Urban Village newsletter Dec 2016 (7.71 MB) (pdf)
-
-
Community engagement information boards and reports