Hercules Street Park construction update - May 2019

Construction completed since our last update
- Completion of bulk earthworks
- Finalisation of stormwater and sewer reticulation
- Retaining wall construction
- Soiling of Kingsford Smith Drive gardens
Construction sequence of works for the next four weeks
- Construction of concrete foot paths
- Installation of pathway lights
- Installation of irrigation tank
- Installation of trees
- Commence amenities building ground works
- Commence erecting picnic shelters