Hercules Street Park construction update - March/April 2019

Construction completed since our last update
- Completion of bulk earthworks
- Finalisation of stormwater and sewer reticulation
- Retaining wall construction
- Soiling of Kingsford Smith Drive gardens
Construction sequence of works for the next four weeks
- Dog off leash fencing
- Ex-ground tree transplanting
- Commence formed concrete landscape walls
- Commence irrigation